PHASE 2A

Regional Hub for petroleum products and bunkering services

Commodity Function tank size (m3) # of tanks capacity (m3) Throughput
ton/year
Fuel Oil Main tanks 20,000 4 80,000 1.5 m
  blending & delivery 10,000 4 40,000 0.8 m
      Total Fuel Oil 120,000 2.3 m
           
Gasoline Main tanks 25,000 2 50,000 1.0 m
  Main tanks 12,500 4 50,000 1.0 m
  Certification & truck delivery 5,000 2 10,000 0.2 m
      Total  Gasoline 110,000 2.2 m
Total throughput across the jetty         4.5 m

 

Additional oil products:

  • Expected additional Throughput: 2,4 million tones/year
  • Additional storage capacity: 2 x 40.000 m3 for fuel oil/gasoil

Bitumen:

  • Expected throughput: 200.000 tones/year
  • Inland distribution by means of trucks
  • Storage capacity: 4 x 5.000 m3


Required Jetty Capacities:

  • One smaller berth for bitumen and Marpol ships up to 20,000 DWT,  also providing additional capacity for bunker barges
  • One berth for additional oil product volume for ships up to50.000 DWT.