PHASE 2B

Regional Hub for Crude Oil

Storage Capacities

Commodity Function tank size (m3) # of tanks capacity (m3) Throughput
ton/year
Crude Oil Main tanks 50,000 10 500,000 5 m
Total Crude Oil       500,000 5 m


Required Jetty Capacities:

  • One berth for large seagoing tankers up to100-120,000 DWT.
  • One berth for VLCC’s